Recently I had a task that seemed very simple at first. I had a table with billing start dates and number of business days to bill. The task was to calculate the end date for each row. Basically to calculate the start date + number of business days without having to worry about holidays.
I was surprised that there is no built-in solution for this seemingly common problem. Here is my own take on the problem.
The logic is quite simple:
- for each 5 working days add an entire calendar week to the starting date
- after adding the whole weeks add the remaining days (for example adding 8 days means adding 1 week and 3 days)
- if the resulting date is a Saturday then add 2 more days
- if the resulting date is a Saturday then add 1 more day
And here is the resulting code:
create function addWorkingDays(@startDate datetime, @workingDays int)
returns datetime
as begin
if @workingDays = 0
return @startDate
declare @calendarDays int =
(@workingDays / 5) * 7 + -- add whole weeks
(@workingDays % 5) -- add remaining days
declare @resultDate datetime = dateadd(d, @calendarDays, @startDate)
declare @dayOfWeek int = ((datepart(DW, @resultdate) - 1) + @@datefirst ) % 7 --the @@datefirst part is needed if you are outside of US where 0 is Monday
return case
when @dayOfWeek = 0 then --Sunday
dateadd(d, @calendarDays, @startDate) + 1
when @dayOfWeek = 6 then -- Saturday
dateadd(d, @calendarDays, @startDate) + 2
else
dateadd(d, @calendarDays, @startDate)
end
end
💖 💪 🙅 🚩